TWIN FALLS — The first two projects to clean up Rock Creek in Twin Falls are moving toward construction. City staff asked the Twin Falls City Council on Monday, Nov. 23, to approve two task orders hiring Jacobs Engineering to design a stormwater project off Shoshone Street and river corridor work at the old College of Southern Idaho fish hatchery, according to the council agenda packet). Staff recommended approval. The city had not posted the outcome of the vote as of this writing.
"It's exciting to actually see some of this stuff starting to happen," Mandi Thompson with the City of Twin Falls told Idaho News 6. "People have been trying to do something about Rock Creek for a really long time."
Project 1: stormwater off Shoshone Street
Task Order 4, for the project the master plan calls Urban Stormwater 2, covers preliminary design, floodplain permit applications, final design and help with bidding. The site is next to the creek off Shoshone Street, and the contract is $382,935, according to the staff memo.
About 45 acres drain into Rock Creek at the Shoshone Street bridge. The project will control that runoff and run it through settling pools to keep phosphorus and other pollutants out of the creek, Idaho News 6 reported. Once design is done, the project will be ready to go out to bid, Thompson said.
Project 2: the old CSI fish hatchery site
Task Order 5, for River Corridor 2, covers preliminary design and a construction cost estimate. The work is in the canyon next to and including the old fish hatchery property the city acquired from CSI. Plans call for reconnecting the creek to its floodplain, stabilizing the banks and improving water quality, and the contract is $247,871. Idaho News 6 reported that removing invasive trees is also part of the plan.
The two contracts total $630,806, which the staff memo says will be fully reimbursed through the Natural Resources Conservation Service (NRCS).
How the Rock Creek effort got here
In 2023 the city received a $4 million congressional appropriation through Rep. Mike Simpson, followed by $1 million more in 2024, to improve water quality in the Rock Creek watershed and the stretch of the Snake River covered by the city's wastewater permit. Jacobs Engineering led a two-year master planning effort covering farming practices, streamside restoration and city stormwater, and the City Council approved the Rock Creek Watershed Master Plan on March 9, 2026, according to the staff memo.
The plan has a prioritized list of 20 projects, and the work will take more than 10 years, Thompson told Idaho News 6. The goal is a creek people can enjoy again, and possibly an urban fishery.
More on Twin Falls
Treasure Idaho has also covered the planned Wendell, Filer and Martin roundabout, the El Milagro housing plan update and the Chobani wellness park and canyon trail junction. See the Twin Falls city guide, browse new home communities in Twin Falls, check homes for sale in Twin Falls, or read more Twin Falls growth news. Thank you for reading Treasure Idaho.
More from Twin Falls
See all- Update: Twin Falls Planners Back Keeping 43 Homes at El Milagro, Sending the Plan to City CouncilTwin Falls · Nov 22, 2026

- Addison Avenue Widening in Twin Falls: City Lands First Right-of-Way Deals for Narrow Stretch Near JuniperTwin Falls · Nov 20, 2026

- Wendell-Filer-Martin Roundabout in Twin Falls Gets $2 Million for Construction, Aims for Summer 2027Twin Falls · Nov 18, 2026

- El Milagro in Twin Falls Seeks to Keep 43 Older Homes, Raising Its Cap to 223Twin Falls · Nov 17, 2026

- New I-84 Lanes Open Near the Twin Falls Interchange as Widening Wraps UpTwin Falls · Nov 10, 2026

- Chobani Wellness Park Opens at Canyon Trail Junction in Twin FallsTwin Falls · Nov 9, 2026