Stoddard Road Widening in Meridian: Road Closes Nov. 30 Near Victory Road as Crews Widen the Ridenbaugh Canal Bridge

Aerial rendering of the widened Stoddard Road in Meridian crossing the Ridenbaugh Canal, with three travel lanes, bike lanes, wide sidewalks, a fenced canal bridge and a crosswalk with a center refuge island
Rendering: Ada County Highway District

Article

The Stoddard Road widening project in Meridian hits its biggest milestone so far on Monday, Nov. 30, when Stoddard Road closes between Victory Road and Grizzly Drive so crews can widen the bridge over the Ridenbaugh Canal. Only local traffic will be allowed on Stoddard between Victory and Overland roads, and the Ada County Highway District expects the stretch to reopen in spring 2027, according to the ACHD project page. ACHD says drivers should use Linder Road or Meridian Road (Idaho 69) to get around the closure.

What the Stoddard Road project includes

ACHD is widening Stoddard Road from Victory Road to Overland Road to three lanes, with center medians where a turn lane is not needed for access. The work includes widening the existing Ridenbaugh Canal bridge and adding curb, gutter and bike lanes on both sides of the road.

Walking and biking get a big upgrade too. The pedestrian hybrid beacon on Stoddard will be moved to line up with Victory Middle School, a new crosswalk with a rectangular rapid flashing beacon will go in north of the canal, and a new pedestrian hybrid beacon and crosswalk will be added on the west leg of Victory Road near Stoddard. A 10-foot-wide multi-use pathway will run along the west side of Stoddard between Victory Road and Kodiak Drive and continue on the south side of Kodiak.

ACHD's bid documents also list a retaining wall, irrigation lines, water main, sewer and fiber optic lines, piping the Hardin Drain and new roadway lighting, along with City of Meridian utility improvements.

Construction timeline

Construction started in mid-November, and ACHD expects the whole project to be finished in fall 2027. The bid documents require all irrigation and bridge work to be done by March 15, 2027, and the rest of the work by Sept. 10, 2027. Crews will generally work from 7 a.m. to 7 p.m., and ACHD says to expect flaggers, significant utility work, noise and dust while the project is underway.

The project has been in the works for years. Design started in 2022, ACHD collected public comments in February 2023, and property purchases for the project took place this year.

What it means for drivers and families

If you use Stoddard to get to Victory Middle School, Overland Road or I-84, plan on the Linder Road or Meridian Road detour through the winter. When the work is done, the corridor will have a center lane, bike lanes, a pathway and safer crossings near the school, KTVB reported.

More on Meridian

Treasure Idaho has also covered phase two of the Linder Road overpass over I-84, The Orchards, BB Living's 159 rental homes, and the Syringa Crossing plan at Meridian and Amity roads. See the Meridian city guide, browse new home communities in Meridian, check homes for sale in Meridian, or read more Meridian growth news. Thank you for reading Treasure Idaho.

Moving guide

Moving to Idaho

A short guide from Treasure Idaho: regions, seasons, jobs, new-home communities, and the questions worth asking before you pick a town. Download it, then poke around the cities and the map.

Then look through the cities and the map.