Boise Airport Master Plan Weighs a New 10,000-Foot Runway South of Gowen Road, Plus Terminal, Road and Parking Changes

Article
BOISE — The Boise Airport master plan update is looking at some of the biggest changes in the airport's history for Boise: a new 10,000-foot runway south of Gowen Road, more terminal and concourse space, a rebuilt Airport Way and thousands of new parking spaces. The options come from planning documents shared with the airport's technical advisory committee and were reported by BoiseDev on Nov. 19. None of the ideas are final, and the airport says there is no timeline or guarantee for any of them.
A master plan is the airport's long-range guide for growth. Boise's update started in 2025, and the final plan is expected around May 2027, according to the project schedule and BoiseDev.
A new runway south of Gowen Road
Today the airport has two runways that sit close together just south of the terminal. The committee presentation lays out planning rules for a future runway: 10,000 feet long, which it says is enough for a Boeing 777, lined up the same way as the current runways, and located south of Gowen Road. Both concepts assume the northern runway, 10L-28R, would close.
Concept No. 1 puts the new runway southeast of the current runways, on land the airport already owns and farther from homes. Concept No. 2 sits farther south. The presentation says that option would be closer to residential areas and may require buying property, but it would add more flight capacity. Both layouts would need new taxiways that cross Gowen Road.
Airport spokesperson Jennifer Kronberg told BoiseDev the current runways are too close together to run at the same time, especially for larger airliners, and that closing the north runway would also free up room for future terminal growth. She said both runway options are still being studied and no preference has been picked.
More terminal and concourse space
These ideas go beyond work already planned, including the new 10-gate Concourse A west of Concourse B described on the airport's BOI Upgrade page. For later growth, the preferred concept would add space east of the pre-security rotunda and extend Concourse B. Other layouts show an L-shaped end, a T between Concourses A and B, and angled or Y-shaped ends on Concourse B, BoiseDev reported.
Airport Way, Wright Street and parking
Road options in the presentation include widening the Airport Way entry and exit to five lanes each, rerouting Wright Street under Vista Avenue or closing its access to the airport, and extending the Airport Way loop to the east. Parking concepts include adding about 2,700 close-in public spaces in expanded garages, adding about 3,600 spaces at the economy lot near Orchard Street and Victory Road, or about 1,040 spaces inside an expanded east loop, where a Best Western and the former Kopper Kitchen now sit.
What happens next
The airport will keep refining the options and choose a preferred development plan before the final master plan is done. Kronberg told BoiseDev that some projects would need other work finished first before they could move ahead. You can follow the update on the Boise Airport master plan page.
More on Boise
Treasure Idaho has also covered the airport's new rental car center and the Pleasant Valley Business Park near the airport. See the Boise city guide, browse new home communities in Boise, check homes for sale in Boise, or read more Boise growth news. Thank you for reading Treasure Idaho.
More from Boise
See all- AC Boise Stadium Expansion Approved: Ada County Clears Path to About 11,000 Seats at Expo IdahoBoise · Nov 21, 2026

- Boise's 8th Street Improvements Project Wraps Up Downtown, With a Ribbon Cutting Set for Nov. 28Boise · Nov 20, 2026

- Owyhee Park Apartments in Boise: 72 Homes Planned on Former Hotel Site Head to City CouncilBoise · Nov 19, 2026

- The Fairview in Boise: 103 Apartments Planned on Former Traveler's Motel Site Go to Design ReviewBoise · Nov 18, 2026

- Brio Vista Subdivision in Boise: 36 Hillside Homes on Hill Road Parkway Go to City CouncilBoise · Nov 17, 2026

- 27th & Fairview Apartments in Boise File Revised Plans for 713 Homes and a 16-Story TowerBoise · Nov 14, 2026